Operator: Highland Council, Scotland Operational: March 2003/Process commissioning almost completed.
This is our latest leachate treatment plant, and is our fourth for the Highland Council.
The plant design flow capacity is 80 m³ /day, and it is the first plant to discharge to s.
Enviros carried provided a full consultancy service handling all elements of the work from design and review of construction, to process commissioning and site operational staff training.